Quick Answer: PortMiami handled a record 10,533,854 cruise passengers in fiscal year 2026 (October 2025 through September 2026), up about 23% from 8,564,225 the year before and the first time it has topped 10 million. Container cargo slipped 0.86% to 1,105,517 TEUs, while the county’s budget documents show a $3.75 billion seaport capital program, a $345 million Royal Caribbean terminal under construction and a $214 million line for the disputed Fisher Island fuel depot.
PortMiami closed its 2026 fiscal year with the biggest cruise number in its history and a cargo number that held just above the one-million mark. The split matters for Miami-Dade businesses: the passenger side of the port is now running far ahead of what the county budgeted, while the container side is steady but no longer growing, and both depend on a capital program, a fuel supply and a leadership team that all changed during the year.
How many cruise passengers did PortMiami handle in fiscal year 2026?
PortMiami counted 10,533,854 cruise passengers in FY2026, which ran from October 1, 2025 to September 30, 2026. That compares with 8,564,225 in FY2025, an increase of 1,969,629 passengers, or about 23%. The port crossed the 10 million mark on September 14, 2026, roughly two weeks before the fiscal year ended.
The prior year had itself been a record. In its December 2025 release, Miami-Dade County reported that FY2025’s 8,564,225 passengers were up 4.02% from 8,233,056 in FY2024. The FY2026 jump is therefore not a rebound from a weak year; it is a step change on top of two consecutive records.
Momentum has continued into the new fiscal year. In October 2026, the first month of FY2027, PortMiami handled 832,142 cruise passengers across 106 cruise calls, its highest October on record. That was up 19.04% from 699,043 passengers in October 2025, while cruise calls rose 13.98% from 93.
What daily and monthly peaks did the port set during the year?
The county’s FY2026-27 Seaport budget document lists a single-day record of 81,364 cruise passengers on April 4, 2026. Monthly figures in the county’s quarterly performance reports show how busy the winter season was: 957,000 passengers in December 2025 against a monthly target of 692,000, and 1,105,000 in March 2026 against the same target.
How much cargo did PortMiami handle in fiscal year 2026?
PortMiami moved 1,105,517 twenty-foot equivalent units (TEUs) of containerized cargo in FY2026, down 0.86% from 1,115,058 TEUs in FY2025, a decline of 9,541 TEUs. The port has now handled more than one million TEUs for 12 consecutive years.
FY2025 had been a growth year, with TEUs up 2.35% from 1,089,443 in FY2024, according to the county. The FY2026 dip is small, and it still beat the FY2025-26 budget assumption of 1,080,000 TEUs by about 2.4%. Monthly reporting showed 89,569 TEUs in December 2025 and 104,470 in March 2026, against a monthly target of 90,000. The first fiscal quarter totaled 270,009 TEUs.
What does the county expect for cargo next year?
The FY2026-27 Seaport budget document sets a cargo target of 1,020,000 TEUs, about 7.7% below the FY2026 actual, and holds the cargo tonnage target at 9.4 million tons, compared with 9.92 million tons in FY2024-25. Budget targets are conservative planning numbers rather than forecasts, but the lower cargo target contrasts with the cruise side, where the port keeps adding calls. The same document describes a cargo incentive program of up to $15 million, funded from Seaport proprietary revenues across FY2025-26 and FY2026-27, which the county expects to be net neutral or positive.
| Measure | FY2024 | FY2025 | FY2026 | FY2026 change |
|---|---|---|---|---|
| Cruise passengers | 8,233,056 | 8,564,225 | 10,533,854 | +23.0% |
| Cargo (TEUs) | 1,089,443 | 1,115,058 | 1,105,517 | -0.86% |
| Budgeted passengers | n/a | n/a | 8,300,000 | Actual 27% above |
| Budgeted TEUs | n/a | n/a | 1,080,000 | Actual 2.4% above |
Sources: Miami-Dade County / PortMiami releases; FY2026-27 Seaport budget document. FY2024 and FY2025 figures as reported in the county’s December 2025 release.
How much revenue did PortMiami earn in FY2026?
Full-year audited revenue for FY2026 has not yet been published. The county’s quarterly performance reports, however, show the port running well ahead of plan through the first half of the fiscal year.
Total seaport operating revenue was $92.0 million in the first quarter (October through December 2025) and $102.4 million in the second quarter (January through March 2026), for a first-half total of $194.5 million against a target of $140 million, roughly 39% above plan. Passenger revenue reached $79.5 million for the half against a $52.6 million target, and cargo revenue reached $42.2 million against a $22.6 million target.
| Revenue line (first half FY2026) | Q1 actual | Q2 actual | Half-year actual | Half-year target |
|---|---|---|---|---|
| Total operating revenue | $92.0M | $102.4M | $194.5M | $140.0M |
| Passenger revenue | $37.5M | $42.0M | $79.5M | $52.6M |
| Cargo revenue | $20.4M | $21.8M | $42.2M | $22.6M |
Source: Miami-Dade County quarterly performance reports, Seaport, periods ending December 31, 2025 and March 31, 2026.
Passenger revenue made up about 41% of first-half operating revenue and cargo about 22%. The port’s economic footprint is larger than its own books: the county’s December 2025 release credited PortMiami with $61 billion in annual economic activity and more than 340,000 jobs.
What does the FY2026-27 budget plan for PortMiami?
Miami-Dade commissioners approved a $14.26 billion countywide budget in September 2026, keeping the operating property tax rate flat at 4.57 mills. PortMiami is an enterprise department funded by its own fees rather than property taxes, and its FY2026-27 Seaport budget document lays out the plan.
The document shows operating expenditures of $182.2 million for FY2026-27, up 2.9% from $177.0 million budgeted for FY2025-26, with total revenues, including carryover, of $760.8 million. Proprietary fees, the money the port charges cruise lines, cargo carriers and tenants, are budgeted at $353.4 million, up from $329.0 million. The department keeps 518 full-time positions, with 65 positions moved from Port Operations into Seaport Facilities in a reorganization.
Are port fees going up?
Yes. The budget document attributes about $14.8 million in added revenue to changes in passenger dockage and wharfage rates, about $1.3 million to cargo dockage and wharfage rates and about $0.7 million to gantry crane charges. The heavier weighting on the passenger side lines up with where the volume growth has been. The document also describes a 2026-2028 cruise market growth initiative expected to have a positive fiscal impact through new berthing agreements.
What capital projects is PortMiami building?
The Seaport capital program totals about $3.75 billion across all years, with $713.2 million scheduled for FY2026-27. Funding leans heavily on borrowing: about $2.22 billion is listed as future financing and $941.7 million as Seaport bonds and loans, with smaller amounts from tenant financing, the U.S. Department of Transportation, the Florida Department of Transportation and the U.S. Army Corps of Engineers.
| Project | Total cost | FY2026-27 amount |
|---|---|---|
| North Bulkhead rehabilitation (Terminals B-G) | $787.3M | $125.8M |
| Royal Caribbean Group Cruise Campus | $621.0M | $29.5M |
| Cruise Terminal G (new) | $344.8M | $149.3M |
| Fuel facility acquisition (Fisher Island) | $214.0M | $214.0M |
| Cruise Terminal Berth 10 | $185.0M | $31.6M |
| Shore power | $177.2M | $11.6M |
| Cruise Terminals AA and AAA | $175.7M | $7.0M |
| Gantry cranes | $119.0M | $1.1M |
| South Florida Container Terminal e-RTG Phase 2 | $100.0M | $21.0M |
| Inspection and fumigation facilities | $56.6M | $50.7M |
Source: Miami-Dade County FY2026-27 Seaport budget document (proposed).
What is Cruise Terminal G and when will it open?
Cruise Terminal G is a $345 million terminal for Royal Caribbean Group, built through a partnership between Miami-Dade County and the cruise company. Ground was broken in January 2026. The single-berth terminal is designed for up to 7,000 passengers and for the company’s largest ships, including Icon-class vessels, while keeping multi-vessel functionality. Plans include a multi-level parking garage and an intermodal transportation facility, and the design-build team is the Lemartec-NV2A joint venture with Perez & Perez Architects & Planners. Completion is targeted for late 2027. The budget document carries $149.3 million for the terminal in FY2026-27, the largest single-year cruise terminal outlay in the plan.
Separately, the Royal Caribbean Group Cruise Campus is budgeted at $621 million, funded by $450 million in Seaport bonds and $171 million in tenant financing. Berth 10, a $185 million cruise terminal project, is planned for completion in FY2028-29.
What is happening on the cargo and environmental side?
The county’s December 2025 release announced completion of the second phase of the electric rubber-tired gantry crane project at the South Florida Container Terminal, bringing the fleet to 18 eRTGs, and noted ongoing drainage and berth rehabilitation work at the Seaboard Marine yard. The budget document reports shore power live at a fifth berth, with more than 300 ship connections to date, and lists new post-Panamax cranes among the department’s key issues.
The plan also carries about $1.7 billion in unfunded needs, led by a $650 million harbor entrance and south channel dredge expansion, a $275 million southside Cruise Terminal K and $200 million in added electrical capacity.
Why is Miami-Dade seizing the Fisher Island fuel depot?
The fuel depot on Fisher Island supplies cruise and cargo ships at PortMiami. Developer HRP Group bought the site for $180 million in 2024 with plans for condominiums. The county was reportedly near a purchase at about $400 million, but Mayor Daniella Levine Cava announced on June 5, 2026 that the county would pursue eminent domain instead after negotiations failed, saying the proposed price was “simply too high.” She said the purchase would be paid with port fees, not tax dollars.
On June 16, 2026, the County Commission voted 12-1 to file eminent domain proceedings for just under 10 acres on Fisher Island. HRP has said it will fight the seizure, and Fisher Island residents have challenged the county’s authority in federal court. The FY2026-27 Seaport budget carries $214 million for the fuel facility acquisition, funded by $150 million in Seaport revenues and $64 million in future financing, and lists long-term fuel access as a key issue for the department.
Who is running PortMiami now?
Leadership turned over mid-year. Director and CEO Hydi Webb’s retirement was announced with immediate effect in early June 2026. Interim director Frederick Wong resigned effective June 30, and Deputy Mayor Roy Coley served as interim director from July 1. On June 24, the mayor named Jonathan Daniels director and CEO, starting August 10, 2026. Daniels most recently led the Maryland Port Administration and Port of Baltimore, including its recovery after the 2024 Francis Scott Key Bridge collapse, and earlier ran Port Everglades.
The record cruise year was largely in place before Daniels arrived, but he inherits the fuel dispute, the Terminal G build-out and a cargo business the county budgets to soften.
Brian’s Take
The headline number is real, but the more useful number is the gap between plan and result. The county budgeted 8.3 million cruise passengers for FY2026 and got 10.5 million. First-half passenger revenue came in about 51% above target. When a public enterprise beats its own plan by that much, it tells me demand moved faster than the people setting the budget expected, and that is good news for the hotels, restaurants, transportation operators and suppliers that live off embarkation days.
Cargo is the part I would watch. It is still above one million TEUs for a twelfth straight year, but it slipped slightly, and the county set next year’s target lower while putting up to $15 million into a cargo incentive program. Meanwhile, the port is raising passenger fees by an estimated $14.8 million and leaning on roughly $3.2 billion of borrowing in its capital plan. That is a bet that cruise volumes keep paying the bills.
The fuel depot is the practical risk. A port that sends out 10 million passengers a year needs dependable fuel, and that question is now in court. For Miami-Dade businesses tied to the port, the record is solid; the open questions are fuel, cargo growth and how smoothly a new director executes a very large construction program.
Frequently Asked Questions
What is PortMiami’s fiscal year?
PortMiami follows Miami-Dade County’s fiscal year, which runs October 1 to September 30. FY2026 covered October 1, 2025 through September 30, 2026.
How fast is PortMiami’s cruise traffic still growing?
October 2026, the first month of FY2027, brought 832,142 passengers on 106 cruise calls, up 19.04% from October 2025 and the port’s best October on record.
Did PortMiami cargo grow in 2026?
No. Container volume fell 0.86% to 1,105,517 TEUs in FY2026, though it remained above one million TEUs for the 12th consecutive year and above the county’s budgeted 1,080,000.
Do property taxes pay for PortMiami?
PortMiami is funded through its own fees, grants and borrowing. The mayor said the Fisher Island fuel depot purchase would be paid with port fees, not tax dollars.
When will Royal Caribbean’s new Terminal G open?
Completion of the $345 million Cruise Terminal G is targeted for late 2027, following a January 2026 groundbreaking.
Sources and Further Reading
- PortMiami Closes FY 2026 With Record 10.5M Cruise Guests — Cruise Industry News
- PortMiami hits new high with 10.5m cruise passenger moves in 2026 — Seatrade Cruise News
- PortMiami Sets New Global Record for Cruise Passenger Traffic (FY2026 cruise and cargo figures) — American Journal of Transportation
- PortMiami posts record cruise and cargo results for Fiscal Year 2025 — Miami-Dade County news release, December 2, 2025
- FY 2026-27 Proposed Budget and Multi-Year Capital Plan, Seaport — Miami-Dade County Office of Management and Budget
- Seaport Quarterly Performance Reports, FY2025-26 Q1 and Q2 — Miami-Dade County
- Royal Caribbean Is Getting a New $345 Million Cruise Terminal in Miami — Caribbean Journal
- PortMiami and Royal Caribbean Break Ground on Cruise Terminal G — Cruise Industry News
- Jonathan Daniels tapped to lead PortMiami at a challenging time — Seatrade Cruise News
- Miami-Dade will take PortMiami fuel facility on Fisher Island by eminent domain — WLRN
- Miami-Dade commission votes to file eminent domain to acquire just under 10 acres on Fisher Island — WPLG Local 10
- Miami-Dade commissioners pass new $14.26B budget — WPLG Local 10